Back-filled with anything possible many years ago , not to mention the old pier rafters still in place this microtunnelling job had it's challenges. This was also a free bore with the sewer pipe being pulled in after the bores were drilled. Average length of the bores was 46m. Pipe diameter 300mm. All 256m of tunneling was completed in record time for MIRVAC. Photos show ground conditions.
This blog spot is for the Development and Futher Advancment of Microtunnelling , Including the Autonomous use of the Robot in the Tunnel Mining Industry. Come share our Passion and Imagination.
Microtunnelling Project in Port Melbourne
Back-filled with anything possible many years ago , not to mention the old pier rafters still in place this microtunnelling job had it's challenges. This was also a free bore with the sewer pipe being pulled in after the bores were drilled. Average length of the bores was 46m. Pipe diameter 300mm. All 256m of tunneling was completed in record time for MIRVAC. Photos show ground conditions.